Planning – Planning Application Documents

Help with this page (opens in a new window)

19/01154/CONDET | Discharge of conditions 3,6,7,8,10,19 of approval ref. 19/00057/FULL - Erection of a fully enclosed non-hazardous/ Commercial and Industrial (C&I) waste processing and refuse derived fuel (RDF) production facility, with associated ancillary facilities, servicing/parking and circulation space and vehicular access. | Land Lying To The North Of St Mark Street St Mark Street Kingston Upon Hull Conditions Partly Discharged
  • Print summary icon
Received
Mon 23 Sep 2019
Validated
Tue 08 Oct 2019
Consultation
Recommendation and/or Committee
Decided
Mon 04 Nov 2019

You can select up to 25 documents to download in one archive file at a time.

Date Published Document Type Description View
30 Mar 2023 Application Form DISCHARGE OF CONDITIONS - 3, 6, 7, 8, 10,19 - PART 4 View document icon
30 Mar 2023 Application Form DISCHARGE OF CONDITIONS - 3, 6, 7, 8, 10,19 - PART 1 View document icon
30 Mar 2023 Application Form DISCHARGE OF CONDITIONS - 3, 6, 7, 8, 10,19 - PART 2 View document icon
30 Mar 2023 Application Form DISCHARGE OF CONDITIONS - 3, 6, 7, 8, 10,19 - PART 3 View document icon
16 Feb 2023 Correspondence ENVIRONMENT AGENCY COMMENTS View document icon
30 Jan 2023 Correspondence EMAILS View document icon
08 Jul 2021 Correspondence ENVIRONMENTAL PROTECTION COMMENTS View document icon
08 Jul 2021 BackGround Papers CONSTRUCTION NOISE ASSESSMENT View document icon
08 Jan 2021 Correspondence EMAIL View document icon
17 Nov 2020 Correspondence GENERAL CORRESPONDENCE View document icon
17 Nov 2020 Correspondence GENERAL CORRESPONDENCE View document icon
03 Aug 2020 Correspondence ENV HEALTH AND AGENT CORRESPONDENCE View document icon
12 Jun 2020 Drawing PILING INFORMATION View document icon
12 Jun 2020 Drawing PILING INFORMATION View document icon
12 Jun 2020 Drawing PILING INFORMATION View document icon
12 Jun 2020 Drawing PILING INFORMATION View document icon
12 Jun 2020 Drawing PILING INFORMATION View document icon
12 Jun 2020 Drawing PILING INFORMATION View document icon
09 Jun 2020 Drawing DRAWING REGISTER View document icon
09 Jun 2020 Drawing PILE DETAILS View document icon
09 Jun 2020 Correspondence E-MAILS WITH AGENT View document icon
09 Jun 2020 Drawing PILE DETAILS View document icon
09 Jun 2020 Drawing PROPOSED SITE LAYOUT View document icon
09 Jun 2020 Drawing EXISTING SERVICES View document icon
19 Mar 2020 Correspondence ENVIRONMENTAL PROTECTION COMMENTS View document icon
18 Dec 2019 Report ENV ACTIVITY REPORT View document icon
18 Dec 2019 Report DRIVEN PILES RAMS INC. View document icon
11 Dec 2019 Correspondence ENV HEALTH COMMENTS View document icon
10 Dec 2019 Correspondence ENVIRONMENTAL HEALTH COMMENTS View document icon
05 Dec 2019 Other COLOUR CHART RE EMAIL RE DISCHARGE OF CONDITION 3 View document icon
05 Dec 2019 Correspondence EMAIL RE DISCHARGE OF CONDITION 3 View document icon
03 Dec 2019 Correspondence ENVIRONMENTAL HEALTH COMMENTS View document icon
20 Nov 2019 Report METHOD STATEMENT DRIVEN PILES View document icon
20 Nov 2019 Report GEMINOR PMP View document icon
20 Nov 2019 Report GEMINOR WASTE FACILITY PILING RAMS View document icon
08 Nov 2019 Correspondence ENVIRONMENT AGENCY COMMENTS View document icon
25 Oct 2019 Correspondence PUBLIC PROTECTION COMMENTS View document icon
17 Oct 2019 Correspondence HIGHWAYS COMMENTS View document icon
04 Oct 2019 Correspondence CONSULTATION ENV HEALTH View document icon
04 Oct 2019 Correspondence HIGHWAYS View document icon
04 Oct 2019 Correspondence CONSULTATION ENVIRONMENT AGENCY View document icon
23 Sep 2019 Report APPENDIX A ESA View document icon
23 Sep 2019 Report APPENDIX B PMP DRAFT View document icon
23 Sep 2019 Correspondence FEE DETAILS REQUIRED View document icon
23 Sep 2019 Application Form ST MARK STREET View document icon
23 Sep 2019 Report APPENDIX D PILING View document icon
23 Sep 2019 Report APPENDIX C METHOD STATEMENT DRIVEN PILES View document icon

Powered by Idox