16/00564/CONDET
|
Discharge of conditions for 13/00061/FULL - 1. Construction of a new surface water pumping station building, including facilities for inspection and removal of pumps, electrical switchrooms and motor control rooms. (42m long x 36m wide x 14.5 (max) high; 137'10" x 108'3" x 47'7"). 2. Demolition of existing pumping station and re-landscaping following completion of new build. 3. Formation of new entrance, access road and pedestrian crossing. 4. Erection of 3m (9'9"0 high security fence. (resubmission) (Revised Design - Height reduced by 1m (3'3"). - condition 4, 6 and 13
|
Bransholme Sewage Works Thomas Clarkson Way Kingston Upon Hull
Application Type | Discharge of condtions |
---|---|
Decision | Conditions Discharged |
Actual Decision Level | Delegated Decision |
Expected Decision Level | Not Available |
Case Officer | Chris Peach |
Ward | Kings Park |
Agent Name | AEW Architects |
Agent Company Name | Not Available |
Environmental Assessment Requested | No |